Clayhill Farm
REPD record 2265. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Anesco
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Central Bedfordshire
- Planning reference
- CB/14/03419/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-08-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-01: Planning Application Submitted
- 2015-01-29: Planning Permission Granted
- 2016-04-24: Under Construction
- 2016-06-24: Operational
- 2018-01-29: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2265. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.