slava.energy: UK renewable energy projects
Paddock Wood
REPD record 2266. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 9.2 MW
- Status
- Operational
- Operator
- Foresight Solar Fund
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Tunbridge Wells
- Planning reference
- 14/502851/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-07-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-05: Planning Application Submitted
- 2014-12-19: Planning Permission Granted
- 2015-02-01: Under Construction
- 2015-03-31: Operational
- 2017-12-19: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2266. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.