Upper Meadowley Farm
REPD record 2272. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10.7 MW
- Status
- Operational
- Operator
- GDL Upper Meadowley
- County
- Shropshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Shropshire
- Planning reference
- 14/03933/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-10-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-28: Planning Application Submitted
- 2015-11-12: Planning Permission Granted
- 2017-01-31: Under Construction
- 2017-03-31: Operational
- 2018-11-12: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2272. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.