Welbeck Colliery
REPD record 2283. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 11.3 MW
- Status
- Operational
- Operator
- Foresight
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Mansfield
- Planning reference
- 2012/0557/NT
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-09-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-02-11: Planning Permission Expired
- 2012-11-21: Planning Application Submitted
- 2013-02-11: Planning Permission Granted
- 2014-03-15: Under Construction
- 2014-07-25: Operational
Open this area on the map