slava.energy: UK renewable energy projects
Priory Farm
REPD record 2284. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.1 MW
- Status
- Operational
- Operator
- Private Developer
- County
- Suffolk
- Region
- Eastern
- Country
- England
- Planning authority
- East Suffolk
- Planning reference
- DC/12/1362/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-10-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-11-27: Planning Application Submitted
- 2013-02-25: Planning Permission Granted
- 2014-03-29: Operational
- 2017-02-25: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2284. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.