slava.energy: UK renewable energy projects
Norrington Common Solar Farm
REPD record 2285. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Terraform Power (SunEdison)
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- W/12/02072/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-11-22: Planning Application Submitted
- 2013-04-25: Planning Permission Granted
- 2014-03-01: Under Construction
- 2014-07-04: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2285. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.