slava.energy: UK renewable energy projects
Littles Manor Farm
REPD record 2293. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 9.5 MW
- Status
- Appeal Refused
- Operator
- The Landmark Practice
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Swale
- Planning reference
- SW/13/0832
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-11-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-07-19: Planning Application Submitted
- 2013-11-22: Planning Permission Refused
- 2014-02-05: Appeal Lodged
- 2014-05-07: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2293. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.