Tealing Airfield PV
REPD record 2295. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 31 MW
- Status
- Planning Permission Expired
- Operator
- Green Cat Renewables
- County
- Tayside
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Angus
- Planning reference
- 14/00428/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-04-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-29: Planning Application Submitted
- 2014-12-11: Planning Permission Granted
- 2017-12-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2295. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.