slava.energy: UK renewable energy projects
Chelwood Solar Farm
REPD record 2298. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Mongoose Energy Coop
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Bath and North East Somerset
- Planning reference
- 14/01895/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-07-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-19: Planning Application Submitted
- 2014-09-12: Planning Permission Granted
- 2015-10-01: Under Construction
- 2015-12-10: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2298. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.