slava.energy: UK renewable energy projects
Coal Pit Lane
REPD record 2322. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.3 MW
- Status
- Planning Application Withdrawn
- Operator
- Phoenix Capital R-Energy Ltd
- County
- Gwent
- Region
- Wales
- Country
- Wales
- Planning authority
- Newport
- Planning reference
- 14/0531
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-11-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-06: Planning Application Submitted
- 2014-10-13: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2322. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.