slava.energy: UK renewable energy projects
Vine Farm Solar Park
REPD record 2329. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 45 MW
- Status
- Operational
- Operator
- Allianz
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- South Cambridgeshire
- Planning reference
- S/1067/14/FL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-09: Planning Application Submitted
- 2014-08-06: Secretary of State - Intervened
- 2014-09-02: Secretary of State - Granted
- 2015-08-01: Under Construction
- 2016-03-15: Operational
- 2017-09-02: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2329. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.