slava.energy: UK renewable energy projects
Capel Grange
REPD record 2337. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10.4 MW
- Status
- Planning Permission Refused
- Operator
- West Coast Energy
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Tunbridge Wells
- Planning reference
- 14/00271/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-09-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-02-03: Planning Application Submitted
- 2014-09-15: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2337. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.