slava.energy: UK renewable energy projects
Higher Bye Farm
REPD record 2342. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.8 MW
- Status
- Operational
- Operator
- Anesco
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 3/26/14/013
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-23: Planning Application Submitted
- 2014-09-26: Planning Permission Granted
- 2015-01-01: Under Construction
- 2015-03-19: Operational
- 2017-09-26: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2342. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.