Stonepit Farm
REPD record 2364. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Lark Energy
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- West Northamptonshire
- Planning reference
- S/2013/1201/MAF
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-09-16: Planning Application Submitted
- 2013-12-24: Planning Permission Granted
- 2014-05-28: Under Construction
- 2014-07-28: Operational
- 2016-12-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2364. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.