Fiskerton Airfield (Phase 1)
REPD record 2369. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 12 MW
- Status
- Operational
- Operator
- NESF (formerly Lark Energy)
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- West Lindsey
- Planning reference
- 130671
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-07-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-11-07: Planning Application Submitted
- 2014-01-30: Planning Permission Granted
- 2014-08-01: Under Construction
- 2015-03-31: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2369. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.