Wellingborough Solar Farm
REPD record 2380. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 8.5 MW
- Status
- Operational
- Operator
- Lark Energy
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North Northamptonshire
- Planning reference
- WP/2013/0372
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-11-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-10-09: Planning Permission Expired
- 2013-07-22: Planning Application Submitted
- 2013-10-09: Planning Permission Granted
- 2013-12-01: Under Construction
- 2014-03-31: Operational