slava.energy: UK renewable energy projects

East Anglia 1 North (EA 4)

REPD record 2471. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Offshore
Capacity
800 MW
Status
Planning Permission Granted
Operator
Scottish Power Renewables
County
Offshore
Region
Offshore
Country
England
Planning authority
The Planning Inspectorate - National Infrastructure
Planning reference
EN010077
Turbines
67
Turbine size
11.9 MW
Record last updated in REPD
2022-04-01

Status history

Dated status events as published by REPD, release Q3 2026.

Position not held by REPD.

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2471. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.