Teeside Offshore Wind Farm
REPD record 2514. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Offshore
- Capacity
- 62 MW
- Status
- Operational
- Operator
- EDF Energy - Northern Offshore Windfarm Ltd
- County
- Offshore
- Region
- Offshore
- Country
- England
- Planning authority
- DECC (S36)
- Planning reference
- R/2004/0305/FF
- Turbines
- 27
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2015-05-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2000-09-17: Planning Permission Expired
- 2005-03-22: Planning Application Submitted
- 2007-09-17: Planning Permission Granted
- 2012-02-01: Under Construction
- 2013-08-31: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2514. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.