Royal Seaforth Dock Wind Farm
REPD record 2574. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 3 MW
- Status
- Operational
- Operator
- Mersey Docks and Harbour Company and Windcluster Limited
- County
- Merseyside
- Region
- North West
- Country
- England
- Planning authority
- Sefton
- Planning reference
- not held by REPD
- Turbines
- 6
- Turbine size
- 0.5 MW
- Record last updated in REPD
- 2003-02-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 1995-10-12: Planning Application Submitted
- 1997-08-22: Planning Permission Granted
- 1999-04-24: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2574. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.