Windmill Hill
REPD record 2584. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 1.5 MW
- Status
- Planning Permission Refused
- Operator
- Ecotricity
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Stroud
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2004-02-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2000-10-06: Planning Application Submitted
- 2001-05-08: Planning Permission Refused
Position not held by REPD.