slava.energy: UK renewable energy projects
Cilciffeth 'A' Wind Farm
REPD record 2643. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 7.8 MW
- Status
- Planning Permission Refused
- Operator
- South Wales Power & SWALEC & National Windpower
- County
- Dyfed
- Region
- Wales
- Country
- Wales
- Planning authority
- Pembrokeshire
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2005-04-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 1999-02-01: Planning Application Submitted
- 1999-10-01: Planning Permission Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2643. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.