slava.energy: UK renewable energy projects
Stud Farm, Rufford (Farm AD)
REPD record 265. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 2.2 MW
- Status
- Operational
- Operator
- Future Biogas
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Newark and Sherwood
- Planning reference
- F/1695
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-04-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2009-09-28: Planning Application Submitted
- 2010-07-05: Planning Permission Granted
- 2016-09-01: Under Construction
- 2017-03-30: Operational
- 2018-07-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 265. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.