slava.energy: UK renewable energy projects
Strath of Brydock - Extension
REPD record 2708. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 2.3 MW
- Status
- Operational
- Operator
- Green Cat Renewables
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2008/2404
- Turbines
- 1
- Turbine size
- 1.3 MW
- Record last updated in REPD
- 2010-06-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2008-11-15: Planning Application Submitted
- 2009-10-16: Planning Permission Granted
- 2009-12-01: Operational
- 2016-07-19: Planning Permission Refused
Position not held by REPD.
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2708. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.