Brockaghboy Wind Farm - extension
REPD record 2888. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Greencoat
- County
- Co. Derry / Londonderry
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Causeway Coast and Glens
- Planning reference
- H/2014/0241/F
- Turbines
- 4
- Turbine size
- 3 MW
- Record last updated in REPD
- 2018-04-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-25: Planning Application Submitted
- 2015-10-27: Planning Permission Granted
- 2016-06-23: Under Construction
- 2017-09-01: Operational
- 2018-10-27: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2888. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.