Pineham AD Plant (Waste AD)
REPD record 296. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 1 MW
- Status
- Abandoned
- Operator
- Renewable Power Systems
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Milton Keynes
- Planning reference
- 10/01181/MIN
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-10-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-06-22: Planning Application Submitted
- 2011-10-12: Planning Permission Granted