North Red Bog
REPD record 2965. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 1.6 MW
- Status
- Operational
- Operator
- Green Cat Renewables
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2007/2794
- Turbines
- 2
- Turbine size
- 0.8 MW
- Record last updated in REPD
- 2009-10-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2007-07-06: Planning Application Submitted
- 2008-03-07: Planning Permission Granted
- 2008-06-23: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2965. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.