Ferrybridge Multifuel 2 (FM2)
REPD record 3. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 70 MW
- Status
- Operational
- Operator
- Scottish and Southern Energy (SSE)
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- The Planning Inspectorate - National Infrastructure
- Planning reference
- EN010061
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-12-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-20: Planning Application Submitted
- 2015-10-28: Planning Permission Granted
- 2016-09-01: Under Construction
- 2019-12-20: Operational
- 2020-10-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.