Carland Cross
REPD record 3005. Status: Decommissioned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 6 MW
- Status
- Decommissioned
- Operator
- Scottish Power Renewables
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- not held by REPD
- Turbines
- 15
- Turbine size
- 0.4 MW
- Record last updated in REPD
- 2015-01-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 1991-05-30: Planning Application Submitted
- 1992-04-29: Planning Permission Granted
- 1992-08-27: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3005. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.