Granox Biogas Plant
REPD record 306. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 5 MW
- Status
- Operational
- Operator
- ReFood UK
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Halton
- Planning reference
- 12/00156/FULEIA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-08-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-10-19: Planning Permission Expired
- 2012-03-21: Planning Application Submitted
- 2012-10-19: Planning Permission Granted
- 2013-01-01: Under Construction
- 2014-06-18: Operational