Ratty's Lane Sustainable Energy Facility (Waste AD)
REPD record 311. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 3 MW
- Status
- Operational
- Operator
- Biogen (formerly Tamar Energy)
- County
- Hertfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Broxbourne
- Planning reference
- 7/0510-10
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-03-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-06-28: Planning Application Submitted
- 2012-03-26: Planning Permission Granted
- 2014-03-31: Under Construction
- 2015-03-26: Planning Permission Expired
- 2016-07-04: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 311. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.