slava.energy: UK renewable energy projects
Crystal Rig Phase 1
REPD record 3114. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 62.5 MW
- Status
- Operational
- Operator
- Fred Olsen Renewables
- County
- Borders
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- 01/00269/FUL
- Turbines
- 25
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2010-04-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2001-04-01: Planning Application Submitted
- 2003-01-22: Planning Permission Granted
- 2004-06-30: Operational
- 2016-01-22: Planning Permission Expired
Position not held by REPD.
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3114. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.