Lewis Wind Farm (Barvas Moor)

REPD record 3139. Status: Planning Permission Refused.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Onshore
Capacity
652 MW
Status
Planning Permission Refused
Operator
Lewis WindPower (a joint venture between British Energy Renewables and AMEC WIND)
County
Western Isles
Region
Scotland
Country
Scotland
Planning authority
Scottish Government (S36)
Planning reference
not held by REPD
Turbines
176
Turbine size
3.09 MW
Record last updated in REPD
2008-04-22

Status history

Dated status events as published by REPD, release Q3 2026.

Position not held by REPD.