slava.energy: UK renewable energy projects

Hunterstone

REPD record 3142. Status: Planning Permission Refused.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Onshore
Capacity
30 MW
Status
Planning Permission Refused
Operator
Scottish Power Renewables
County
Strathclyde
Region
Scotland
Country
Scotland
Planning authority
North Ayrshire
Planning reference
N/03/0076/PP
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2015-11-24

Status history

Dated status events as published by REPD, release Q3 2026.

Position not held by REPD.

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3142. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.