slava.energy: UK renewable energy projects

Blaengwen Farm

REPD record 3289. Status: Revised.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Onshore
Capacity
30.2 MW
Status
Revised
Operator
CATAMOUNT CYMRU CYF (agent ENTEC UK Ltd) Force 9 Energy
County
Dyfed
Region
Wales
Country
Wales
Planning authority
Carmarthenshire
Planning reference
W/09205
Turbines
10
Turbine size
3 MW
Record last updated in REPD
2005-10-27

Status history

Dated status events as published by REPD, release Q3 2026.

Position not held by REPD.

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3289. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.