Bowbeat Emly Bank / Rough Side

REPD record 3299. Status: Operational.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Onshore
Capacity
31.2 MW
Status
Operational
Operator
PowerGen and Natural Power
County
Borders
Region
Scotland
Country
Scotland
Planning authority
Scottish Borders
Planning reference
00/00371/FUL
Turbines
24
Turbine size
1.3 MW
Record last updated in REPD
2011-02-10