slava.energy: UK renewable energy projects
Milnathort Community Wind Cluster
REPD record 3350. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 2.4 MW
- Status
- Appeal Refused
- Operator
- Lomond Energy
- County
- Tayside
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 12/01765/FLL
- Turbines
- 3
- Turbine size
- 0.8 MW
- Record last updated in REPD
- 2014-01-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-10-03: Planning Application Submitted
- 2013-08-07: Planning Permission Refused
- 2014-01-07: Appeal Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3350. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.