slava.energy: UK renewable energy projects
Aberarder Wind Farm
REPD record 3371. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 49.9 MW
- Status
- Under Construction
- Operator
- Scottish & Southern Energy
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 15/00737/FUL
- Turbines
- 12
- Turbine size
- 3 MW
- Record last updated in REPD
- 2023-08-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-03-03: Planning Application Submitted
- 2016-04-19: Planning Permission Refused
- 2016-07-14: Appeal Lodged
- 2017-04-07: Appeal Granted
- 2017-04-07: Planning Permission Granted
- 2022-04-01: Planning Permission Expired
- 2023-03-01: Under Construction
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3371. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.