slava.energy: UK renewable energy projects
Blaise Farm (Farm AD)
REPD record 338. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 5 MW
- Status
- Abandoned
- Operator
- PandaGreen
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Tonbridge and Malling
- Planning reference
- 12/02549/WAS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-10-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-08-13: Planning Application Submitted
- 2013-04-16: Planning Permission Expired
- 2013-04-16: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 338. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.