Torr Works
REPD record 3428. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 3.6 MW
- Status
- Appeal Refused
- Operator
- Aggregate Industries UK
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 2013/1244
- Turbines
- 4
- Turbine size
- 0.9 MW
- Record last updated in REPD
- 2015-01-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-06-24: Planning Application Submitted
- 2014-04-16: Planning Permission Refused
- 2014-11-04: Appeal Lodged
- 2016-01-25: Appeal Refused
Position not held by REPD.