slava.energy: UK renewable energy projects
Gordonbush (extension)
REPD record 3435. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 47 MW
- Status
- Operational
- Operator
- Scottish and Southern Energy (SSE)
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- EC00003105
- Turbines
- 11
- Turbine size
- 4.3 MW
- Record last updated in REPD
- 2026-01-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-01: Planning Application Submitted
- 2017-09-29: Planning Permission Granted
- 2020-05-01: Under Construction
- 2021-01-01: Operational
- 2024-09-29: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3435. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.