Hill Of Lychrobbie
REPD record 3436. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 2.4 MW
- Status
- Planning Permission Expired
- Operator
- Wind Harvest
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 13/04194/FUL
- Turbines
- 3
- Turbine size
- 0.8 MW
- Record last updated in REPD
- 2020-06-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-11-07: Planning Application Submitted
- 2016-03-30: Planning Permission Refused
- 2016-06-23: Appeal Lodged
- 2017-01-26: Appeal Granted
- 2017-01-26: Planning Permission Granted
- 2024-04-16: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3436. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.