slava.energy: UK renewable energy projects
Largie Wind Farm
REPD record 3451. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 14.9 MW
- Status
- Planning Permission Refused
- Operator
- Eurus Energy & Ecogen
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Argyll and Bute
- Planning reference
- 94/00772/DET
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2004-08-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 1994-08-24: Planning Application Submitted
- 1998-11-17: Planning Permission Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3451. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.