Pontefract Wind Farm
REPD record 3455. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 12 MW
- Status
- Appeal Refused
- Operator
- Banks Development
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Wakefield
- Planning reference
- 07/01338/FUL
- Turbines
- 6
- Turbine size
- 2 MW
- Record last updated in REPD
- 2010-12-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2007-05-03: Planning Application Submitted
- 2008-02-01: Planning Permission Refused
- 2010-06-22: Appeal Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3455. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.