Whitelee
REPD record 3489. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 322 MW
- Status
- Operational
- Operator
- CRE Energy& Scottish Power
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- 2002/0001/EB
- Turbines
- 140
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2010-05-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2002-01-23: Planning Application Submitted
- 2006-04-01: Planning Permission Granted
- 2006-12-01: Under Construction
- 2007-12-14: Operational
- 2013-04-01: Planning Permission Expired
Position not held by REPD.
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3489. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.