slava.energy: UK renewable energy projects
Gedling Colliery AD
REPD record 360. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 3 MW
- Status
- Abandoned
- Operator
- Biogen (formerly Tamar Energy)
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Gedling
- Planning reference
- 2014/1025NCC
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-03-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-22: Planning Application Submitted
- 2014-10-02: Planning Permission Granted
- 2015-03-15: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 360. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.