slava.energy: UK renewable energy projects
Honey Hill
REPD record 3604. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 2 MW
- Status
- Planning Application Withdrawn
- Operator
- Wind Prospect
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Fenland
- Planning reference
- F/99/0412/f
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2006-04-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 1999-08-02: Planning Application Submitted
- 2006-04-24: Planning Application Withdrawn
Position not held by REPD.