Red Tile
REPD record 3608. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 24 MW
- Status
- Operational
- Operator
- Wind Prospect Developments
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Huntingdonshire
- Planning reference
- 0302827FUL
- Turbines
- 12
- Turbine size
- 2 MW
- Record last updated in REPD
- 2017-12-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-10-15: Planning Application Submitted
- 2005-02-07: Planning Permission Granted
- 2006-05-01: Under Construction
- 2006-12-01: Operational
Position not held by REPD.