Craigton and Spittalhill Wind Farm
REPD record 3625. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 21 MW
- Status
- Planning Permission Expired
- Operator
- Force 9 Energy LLP and EDF Energy
- County
- Stirling
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Stirling
- Planning reference
- 13/00728/FUL
- Turbines
- 7
- Turbine size
- 3 MW
- Record last updated in REPD
- 2019-07-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-12-05: Planning Application Submitted
- 2015-03-24: Planning Permission Refused
- 2015-06-23: Appeal Lodged
- 2015-11-17: Appeal Granted
- 2015-11-17: Planning Permission Granted
- 2018-11-17: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3625. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.