slava.energy: UK renewable energy projects
Church House Wind Farm
REPD record 3632. Status: Appeal Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 4 MW
- Status
- Appeal Withdrawn
- Operator
- Airvolution Energy
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Cumberland
- Planning reference
- 4/14/2105/0F1
- Turbines
- 2
- Turbine size
- 2 MW
- Record last updated in REPD
- 2015-09-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-31: Planning Application Submitted
- 2015-07-20: Appeal Lodged
- 2015-08-20: Appeal Withdrawn
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3632. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.