slava.energy: UK renewable energy projects
Maerdy extension
REPD record 3643. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 3 MW
- Status
- Abandoned
- Operator
- Greencoat UK Wind
- County
- Mid Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Rhondda Cynon Taf
- Planning reference
- 14/0556/10
- Turbines
- 1
- Turbine size
- 3 MW
- Record last updated in REPD
- 2015-05-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-01: Planning Application Submitted
- 2014-12-22: Planning Permission Granted
- 2015-02-09: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3643. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.